How to Fill and Submit Engineer's Certificate Form (Form 2) for MahaRERA Projects

Are you involved in ongoing projects registered under MahaRERA? Understanding and accurately submitting the Engineer's Certificate Form (Form 2) is crucial for compliance. In this detailed guide, we'll provide step-by-step instructions on filling and submitting Form 2, ensuring seamless adherence to MahaRERA regulations.

1. Accessing the Form:

  • Begin by accessing Form 2 directly from the official MahaRERA website here.
  • Ensure you have the latest version of the form for accurate information submission.

2. Understanding the Form:

  • Form 2 is a mandatory document to be submitted at the time of project registration and for withdrawal of funds from the designated account.
  • It certifies the cost incurred for the development of the project.

3. Filling Out the Form:

  • Start by entering the date of submission and addressing it to the promoter.
  • Provide details such as the project name, MahaRERA registration number, and the name and address of the promoter.

4. Estimating Costs:

  • If you're an engineer assigned to certify the estimated cost, accurately fill out the sections related to cost estimation.
  • Estimate the cost of civil, MEP (Mechanical, Electrical, Plumbing), and allied works required for the completion of apartments and proportional completion of internal and external works of the project.

5. Detailed Breakdown:

  • Provide a detailed breakdown of the estimated costs based on the drawings/plans provided by the developer/consultants and site inspections.
  • Estimate the total cost of construction and the balance cost to be incurred based on the work completed and yet to be completed.

6. Completing Tables A and B:

  • Table A focuses on the estimated cost of the building/wing/layout/plotted development, detailing the total estimated cost, cost incurred, percentage of work done, and balance cost.
  • Table B covers internal and external development works, including amenities and facilities, with similar details as Table A.

7. Additional/Deleted Items:

  • In Table C, list any additional, extra, or deleted items considered in the cost estimation, which were not part of the original estimate of the total cost.

8. Signature and Acceptance:

  • Sign and print your name (in block letters) along with your stamp as an engineer.
  • Obtain the signature of the promoter, indicating their agreement and acceptance of the certification.

9. Submission Process:

  • Once the form is duly filled and signed, submit it as per the guidelines provided by MahaRERA.
  • Ensure all necessary documents and approvals are attached to support the information provided in the form.

By following these steps diligently, you can accurately fill and submit the Engineer's Certificate Form (Form 2) for MahaRERA projects, ensuring compliance with regulatory requirements. Stay updated with any changes or updates to the form or submission process through official channels to maintain compliance.